89 FR 64 pg. 22704 - Kaukauna Utilities; Notice of Intent To Prepare an Environmental Assessment

Type: NOTICEVolume: 89Number: 64Page: 22704
Docket number: [Project No. 2715-026]
FR document: [FR Doc. 2024-06873 Filed 4-1-24; 8:45 am]
Agency: Energy Department
Sub Agency: Federal Energy Regulatory Commission
Official PDF Version:  PDF Version
Page: 22704

[top] page 22704

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2715-026]

Kaukauna Utilities; Notice of Intent To Prepare an Environmental Assessment

On July 22, 2022, Kaukana Utilities (Kaukauna) filed a relicense application for the 6.2-megawatt Combined Locks Hydroelectric Project No. 2715 (project). The project is located on the Lower Fox River in the Village of Combined Locks and the Village of Little Chute, Outagamie County, Wisconsin.

In accordance with the Commission's regulations, on January 16, 2024, Commission staff issued a notice that the project was ready for environmental analysis (REA Notice). Based on the information in the record, including comments filed on the REA Notice, staff does not anticipate that licensing the project would constitute a major federal action significantly affecting the quality of the human environment. Therefore, staff intends to prepare an Environmental Assessment (EA) on the application to relicense the project.

The EA will be issued and circulated for review by all interested parties. All comments filed on the EA will be analyzed by staff and considered in the Commission's final licensing decision.

The Commission's Office of Public Participation (OPP) supports meaningful public engagement and participation in Commission proceedings. OPP can help members of the public, including landowners, environmental justice communities, Tribal members and others, access publicly available information and navigate Commission processes. For public inquiries and assistance with making filings such as interventions, comments, or requests for rehearing, the public is encouraged to contact OPP at (202) 502-6595 or OPP@ferc.gov.

The application will be processed according to the following schedule. Revisions to the schedule may be made as appropriate.

Milestone Target date
Commission issues EA August 2024. 1
Comments on EA October 2024.

Any questions regarding this notice may be directed to Kelly Wolcott at (202) 502-6480 or kelly.wolcott@ferc.gov.

Footnotes:

1 ?The Council on Environmental Quality's (CEQ) regulations under 40 CFR 1501.10(b)(1) (2023) require that EAs be completed within 1 year of the Federal action agency's decision to prepare an EA. See National Environmental Policy Act, 42 U.S.C. 4321 et seq., as amended by section 107(g)(1)(B)(iii) of the Fiscal Responsibility Act of 2023, Public Law 118-5, section 4336a, 137 Stat. 42.

Dated: March 26, 2024.

Debbie-Anne A. Reese,

Acting Secretary.

[FR Doc. 2024-06873 Filed 4-1-24; 8:45 am]