[top] page 7432

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 4718-000]

Cocheco Falls Associates; Notice of Authorization for Continued Project Operation

The license for the Cocheco Falls Dam Hydroelectric Project No. 4718 was issued for a period ending December 31, 2022.

Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), requires the Commission, at the expiration of a license term, to issue from year-to-year an annual license to the then licensee(s) under the terms and conditions of the prior license until a new license is issued, or the project is otherwise disposed of as provided in section 15 or any other applicable section of the FPA. If the project's prior license waived the applicability of section 15 of the FPA, then, based on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), and as set forth at 18 CFR 16.21(a), if the licensee of such project has filed an application for a subsequent license, the licensee may continue to operate the project in accordance with the terms and conditions of the license after the minor or minor part license expires, until the Commission acts on its application. If the licensee of such a project has not filed an application for a subsequent license, then it may be required, pursuant to 18 CFR 16.21(b), to continue project operations until the Commission issues someone else a license for the project or otherwise orders disposition of the project.

If the project is subject to section 15 of the FPA, notice is hereby given that an annual license for Project No. 4718 is issued to Cocheco Falls Associates for a period effective January 1, 2023, through December 31, 2023, or until the issuance of a new license for the project or other disposition under the FPA, whichever comes first. If issuance of a new license (or other disposition) does not take place on or before December 31, 2023, notice is hereby given that, pursuant to 18 CFR 16.18(c), an annual license under section 15(a)(1) of the FPA is renewed automatically without further order or notice by the Commission, unless the Commission orders otherwise.


[top] If the project is not subject to section 15 of the FPA, notice is hereby given that Cocheco Falls Associates is authorized to continue operation of the Cocheco Falls Dam Hydroelectric Project under the terms and conditions of the prior license until the issuance of page 7433 a new license for the project or other disposition under the FPA, whichever comes first.

Dated: January 30, 2023.

Kimberly D. Bose,

Secretary.

[FR Doc. 2023-02298 Filed 2-2-23; 8:45 am]

BILLING CODE 6717-01-P