DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 6951-018]

Tallassee Shoals, LLC; Notice of Revised Procedural Schedule for Environmental Assessment for the Proposed Project Relicense

On September 15, 2021, Tallassee Shoals, LLC. filed an application for a new license to continue to operate and maintain the 2.3-megawatt Tallassee Shoals Hydroelectric Project No. 6951 (Tallassee Shoals Project). On September 14, 2022, Commission staff issued a notice of intent to prepare an Environmental Assessment (EA) to evaluate the effects of relicensing the Tallassee Shoals Project. The notice of intent included a schedule for preparing a draft and final EA.

By this notice, Commission staff is updating the procedural schedule for completing a final EA. The revised schedule is shown below. Further revisions to the schedule may be made as appropriate.

Milestone Target date
Issue EA January 2024.

Any questions regarding this notice may be directed to Michael Spencer at (202) 502-6093, or by email at michael.spencer@ferc.gov.

Dated: October 27, 2023.

Debbie-Anne A. Reese,

Deputy Secretary.