80 FR 162 pgs. 50848-50849 - Igiugig Village Council; Notice Concluding Pre-Filing Process and Approving Process Plan and Schedule
Type: NOTICEVolume: 80Number: 162Pages: 50848 - 50849
Pages: 50848, 50849Docket number: [Project No. 13511-002]
FR document: [FR Doc. 2015-20745 Filed 8-20-15; 8:45 am]
Agency: Energy Department
Sub Agency: Federal Energy Regulatory Commission
Official PDF Version: PDF Version
[top]
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 13511-002]
Igiugig Village Council; Notice Concluding Pre-Filing Process and Approving Process Plan and Schedule
a. Type of Filing: Notice of Intent to File an Application for a Hydrokinetic Pilot Project.
b. Project No.: 13511-002.
c. Date Filed: April 1, 2015.
d. Submitted By: Igiugig Village Council (Igiugig).
e. Name of Project: Igiugig Hydrokinetic Project.
f. Location: On the Kvichak River in the Lake and Peninsula Borough, near the town of Igiugig, Alaska. The project would not occupy any federal lands.
g. Filed Pursuant to: 18 CFR 5.3 and 5.5 of the Commission's regulations.
h. Applicant Contact: AlexAnna Salmon, President, Igiugig Village Council, P.O. Box 4008, Igiugig, Alaska 99613; (907) 533-3211.
i. FERC Contact: Dianne Rodman (202) 502-6077.
[top] j. Igiugig has filed with the Commission: (1) A notice of intent to file an application for a pilot hydrokinetic hydropower project and a draft license application with monitoring plans; (2) a request for waivers of certain Integrated Licensing Process regulations necessary for
k. A notice was issued on April 23, 2015, soliciting comments on the draft license application from agencies and stakeholders. Comments were filed by non-governmental organizations and individuals.
l. On April 23, 2015, Igiugig was designated as the non-federal representative for section 7 consultation under the ESA and for section 106 consultation under the National Historic Preservation Act.
m. The proposed Igiugig Hydrokinetic Project would consist of: (1) An in-stream 20- kilowatt (kW), 64-foot-long, 11-foot-high, 43-foot-wide pontoon-mounted RivGen Power System Turbine Generator Unit (TGU) in Phase 1; (2) an additional in-stream 20-kW pontoon-mounted TGU in Phase 2; (3) two anchoring systems consisting of a 13,000-pound anchor, chain, shackles, and 150 feet of mooring; (4) a 375-foot-long, coated and weighted combined power, data, and environmental monitoring cable from the TGU for Phase 1; and a 675-foot-long cable from the TGU for Phase 2; (5) an existing 10-foot-long by 8-foot-wide shore station for housing project electronics and Issue biological assessment February 15, 2015.
n. controls; and (6) appurtenant facilities. The project is estimated to have an annual generation of 409,504 kilowatt-hours.
o. The pre-filing process has been concluded and the requisite regulations have been waived such that the process and schedule indicated below can be implemented.
p. The post-filing process will be conducted pursuant to the following schedule. Revisions to the schedule may be made as needed.
Milestones | Dates |
---|---|
Final license application expected | November 2, 2015. |
Issue notice of acceptance and ready for environmental analysis and request for interventions | November 17, 2015. |
Recommendations, Conditions, Comments and Interventions due | December 17, 2015. |
Issue notice of availability of environmental assessment | February 15, 2016. |
Issue biological assessment | February 15, 2016. |
Comments due and 10(j) resolution, if needed | March 16, 2016. |
q. Register online at http://ferc.gov/esubscribenow.htm to be notified via email of new filing and issuances related to this or other pending projects. For assistance, contact FERC Online Support.
Dated: August 17, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-20745 Filed 8-20-15; 8:45 am]
BILLING CODE 6717-01-P