80 FR 194 pgs. 60647-60657 - One-Time Deauthorization of Water Resources Projects
Type: NOTICEVolume: 80Number: 194Pages: 60647 - 60657
Pages: 60647, 60648, 60649, 60650, 60657FR document: [FR Doc. 2015-25586 Filed 10-6-15; 8:45 am]
Agency: Defense Department
Sub Agency: Army Department; Engineers Corps
Official PDF Version: PDF Version
[top]
DEPARTMENT OF DEFENSE
Department of the Army; Corps of Engineers
One-Time Deauthorization of Water Resources Projects
AGENCY:
Army Corps of Engineers, DoD.
ACTION:
Notice of Interim Deauthorization List.
SUMMARY:
The U.S. Army Corps of Engineers is publishing an Interim Deauthorization List of water resources development projects and separable elements that have been identified for deauthorization in accordance with section 6001(c) of the Water Resources Reform and Development Act of 2014, Public Law 113-121, 128 STAT. 1346-1347 (WRRDA 2014), and is soliciting comments from the public on the list for 90 calendar days. Comments should be provided to the contact named below by January 4, 2016.
FOR FURTHER INFORMATION CONTACT:
Mr. Joseph W. Aldridge, Headquarters, U.S. Army Corps of Engineers, Attention: CECW-IP, Washington, DC 20314-1000. Tel. (202) 761-4130 or joseph.w.aldridge@usace.army.mil .
SUPPLEMENTARY INFORMATION:
Interim Deauthorization List required by § 6001(c).
Section 6001(c) provides that the Secretary shall develop an Interim Deauthorization List that identifies each water resources development project, or separable element of a project, that meets the following criteria. Projects and separable elements eligible for deauthorization are those uncompleted construction projects and separable elements meeting all of the following criteria: (1) They were authorized for construction before November 8, 2007, or their most recent modification of the construction authorization predates November 8, 2007; (2) their construction has not been initiated, or, if construction has been initiated, there have been no obligations of Federal or non-federal funds for construction in the current fiscal year or any of the past 6 fiscal years; and, (3) there has been no funding for a post-authorization study in the current fiscal year or any of the past 6 fiscal years. As specifically provided in section 6001(f)(1)(B) of WRRDA 2014, water resources development projects include environmental infrastructure assistance projects and programs of the U.S. Army Corps of Engineers. In accordance with section 103(f) of the Water Resources Development Act of 1986, separable elements is defined as "a portion of a project-
(1) which is physically separable from other portions of the project; and
(2) which-
(A) achieves hydrologic effects, or
(B) produces physical or economic benefits, which are separately identifiable from those produced by other portions of the project."
The following elements of an authorized water resources development project also qualify as separable elements: An element for which there is an executed design agreement or project partnership agreement specific to that element; an element that has received funding specified for that element; an element that was authorized separately from or as an amendment to the authorization for the remainder of the water resources development project, that was separately identified in the authorization for the water resources development project, or for which a statute specifies an authorized cost, estimated cost, or amount authorized to be appropriated; an element that has been placed in service or for which the Government or the non-federal partner has assumed operation and maintenance; an element that has been deauthorized; or the remaining portion of the water resources development project apart from other separable elements. Following a 90-day public review period of the Interim Deauthorization List, the Assistant Secretary of the Army for Civil Works (ASA(CW)) will publish a Final Deauthorization List in the Federal Register . Section 6001(d)(2)(A) of WRRDA 2014 requires that the Secretary shall include on the Final Deauthorization List projects and separable elements of projects that have, in the aggregate, an estimated Federal cost to complete that is at least $18 billion. The ASA(CW) has strived to meet the requirements of Section 6001, but was not able to identify projects that totaled $18 billion.
[top] The projects and elements on the Final Deauthorization List will be deauthorized automatically after 180 days following the date that the ASA(CW) submits the Final Deauthorization List to Congress, unless
[top] The Interim Deauthorization List follows below in Table 1.
[top]
State | Business line | Corps district | Congressional districts | Project/element name | Project/element type(1) | Public law of authorization or latest amendment | Section of public law | Project/element phase and status(2) | Latest fiscal year of federal or non-federal obligations for construction | Federal balance to complete (subject to Section 902 where applicable) |
---|---|---|---|---|---|---|---|---|---|---|
AL | NAV | SAM | AL 2, 3 & 4 | ALABAMA-COOSA RIVER AND TRIBUTARIES, AL (COOSA RIVER BETWEEN MONTGOMERY AND GADSDEN) | PROJECT | 99-662 | 813 | CONSTRUCTION NOT INITIATED | 1986 | $3,781,921,691 |
AL | EI | SAM | AL 4 | DUCK RIVER, AL | PROJECT | 106-554 | 108a | CONSTRUCTION NOT INITIATED | NO OBLIGATION FOR CONSTRUCTION | 5,000,000 |
AR | EI | MVK | AR 4 | UNION COUNTY, AR | PROJECT | 106-554 | 108d | CONSTRUCTION NOT INITIATED | 2008 | 51,247,100 |
AR | FRM | MVM | AR 1 | L'ANGUILLE RIVER BASIN, AR | PROJECT | 99-662 | 103 | CONSTRUCTION NOT INITIATED | 2004 | 19,466,768 |
AR | FRM | SWL | AR 1, 2, 3 & 4; OK 1 | ARKANSAS RIVER LEVEES, AR | PROJECT | 101-640 | 110(a1) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 591,605 |
AR | AER | SWL | AR 3 | BEAVER DAM , AR (TROUT PRODUCTION CENTER) | SEPARABLE ELEMENT | 94-587 | 105 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 5,990,000 |
AR | EI | SWL | AR 3 | BEAVER LAKE, BENTON/WASH, AR | SEPARABLE ELEMENT | 104-303 | 523 | CONSTRUCTION PAUSED | 2002 | 5,000,000 |
CA | EI | SPK | CA 4 | CALAVERAS COUNTY, CA | PROJECT | 104-303 | 526 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,500,000 |
CA | EI | SPK | CA 3 & 5 | CLEAR LAKE BASIN, CA | PROJECT | 106-554 | 108a | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,543,324 |
CA | FRM | SPK | CA 3 | COLUSA TROUGH DRAINAGE CANAL, SACRAMENTO RIVER AND TRIBUTARIES, CA | PROJECT | 99-662 | 830 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 18,900,846 |
CA | EI | SPK | CA 21 | PINE FLAT DAM, CA | PROJECT | 106-541 | 101b(7) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 41,502,918 |
CA | EI | SPL | CA 39 | CHINO HILLS, CA | PROJECT | 106-554 | 108a | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,543,324 |
CA | EI | SPL | CA 39 & 45 | EASTERN MUNICIPAL WATER DISTRICT, CA | PROJECT | 106-554 | 108a | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,543,324 |
CA | FRM | SPL | CA 24 | GOLETA & VICINITY, CA | PROJECT | 102-580 | 102b | CONSTRUCTION PAUSED | 1984 | 1,233,626 |
CA | EI | SPL | CA 44 | LOS ANGELES HARBOR/TERMINAL ISLAND, CA | PROJECT | 106-554 | 108d | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 6,500,000 |
CA | FRM | SPL | CA 24 | LOWER MISSION CREEK, CA | PROJECT | 100-676 | 3a | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 14,625,971 |
CA | EI | SPL | CA 26, 27 & 29 | SAN DIEGO AREA WATER REUSE DEMOSTRATION FACILITIES, CA | PROJECT | 102-580 | 217c(2) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 5,000,000 |
CA | EI | SPL | CA 52 | SAN DIEGO COUNTY, CA (CORONADO TRANSBAY WASTEWATER PIPELINE) | PROJECT | 106-554 | 108d | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 10,000,000 |
CA | EI | SPL | CA 26, 27 & 29 | SOUTHERN CALIFORNIA COMPREHENSIVE WATER REUSE SYSTEM, CA | PROJECT | 102-580 | 217c(1) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 5,000,000 |
CT | EI | NAE | CT 4 | BRIDGEPORT COMBINED SEWER OVERFLOW PTOJECT, CT | PROJECT | 106-53 | 502b | CONSTRUCTION NOT INITIATED | NO OBLIGATION FOR CONSTRUCTION | 10,000,000 |
CT | EI | NAE | CT 1 | HARTFORD, CT | PROJECT | 106-53 | 502b | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 10,000,000 |
CT | EI | NAE | CT 3 | NEW HAVEN, CT | PROJECT | 106-53 | 502b | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 10,000,000 |
CT, ME, MA, NH, RI & VT | AER | NAE | CT 1, 2, 3, 4 & 5; ME 1, & 2; MA 1, 2, 3, 4, 5, 6, 7, 8, & 9; NH 1 & 2; RI 1 & 2; VT AT LARGE | NEW ENGLAND WATER RESOURCES AND ECOSYSTEM RESTORATION, CT, ME, MA, NH, RI & VT | PROJECT | 106-541 | 507 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | (3)0 |
DC & MD | EI | NAB | WASHINGTON DC AND MARYLAND, D.C. & MD | PROJECT | 106-554 | 108d | CONSTRUCTION NOT INITIATED | 1998 | 14,807,000 | |
FL | AER | SAJ | FL 17, 18, 19, 20, 21, 22 & 23 | COMPREHENSIVE EVERGLADES RESTORATION PLAN, FL (LAKE BELT GROUND RESERVOIR TECHNOLOGY) | SEPARABLE ELEMENT | 106-541 | 601 b2biiii | CONSTRUCTION NOT INITIATED | 2005 | 17,000,000 |
FL | AER | SAJ | FL 17, 18, 20, 21, 22, 23, 25, 26 & 27 | COMPREHENSIVE EVERGLADES RESTORATION PLAN, FL (NORTH NEW RIVER IMPROVEMENTS) | SEPARABLE ELEMENT | 106-541 | 601 b2cix | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 67,150,000 |
FL | AER | SAJ | FL 18, 20, 21, 22, 23, 24, 25, 26 & 27 | COMPREHENSIVE EVERGLADES RESTORATION PLAN, FL (RAISE AND BRIDGE EAST PORTION OF TAMIAMI TRAIL AND FILL MIAMI CANAL WITHIN WATER) (CONSEVATION AREA 3) | SEPARABLE ELEMENT | 106-541 | 601 b2cviii | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 21,500,000 |
FL | AER | SAJ | FL 16 & 23 | COMPREHENSIVE EVERGLADES RESTORATION PLAN, FL (TAYLOR CREEK/NUBBIN SLOUGH STORAGE AND TREATMENT AREA) | SEPARABLE ELEMENT | 106-541 | 601 b2cvii | CONSTRUCTION NOT INITIATED | NO OBLIGATION FOR CONSTRUCTION | 67,800,000 |
FL | AER | SAJ | FL 17, 18, 20, 21, 22, 23, 25, 26 & 27 | COMPREHENSIVE EVERGLADES RESTORATION PLAN, FL (WASTEWATER REUSE TECHNOLOGY) | SEPARABLE ELEMENT | 106-541 | 601 b2biiii | CONSTRUCTION NOT INITIATED | 2005 | 20,500,000 |
FL | NAV | SAJ | FL 12 | HUDSON RIVER, FL | PROJECT | 81-516 | 101 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 3,650,000 |
FL | EI | SAJ | FL 27 | KEY BISCAYNE, FL | PROJECT | 106-554 | 108a | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,543,324 |
FL | FRM | SAJ | FL 14 | LITTLE TALBOT ISLAND, FL | PROJECT | 106-53 | 101b7 | CONSTRUCTION PAUSED | 2000 | 6,786,030 |
FL | EI | SAJ | FL 14 | SOUTH TAMPA, FL | PROJECT | 106-554 | 108a | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,543,324 |
FL | NAV | SAJ | FL 10, 11, 12 & 13 | TAMPA HARBOR, ALAFIA RIVER, FL | PROJECT | 106-554 | 107 | CONSTRUCTION NOT INITIATED | 2006 | 64,771,847 |
FL | NAV | SAJ | FL 10, 11, 12 & 13 | TAMPA HARBOR, FL ((PORT SUTTON TURNING BASIN) WIDENING TO AN ADDITIONAL 105 FEET TO THE FENDER LINE ALONG PENDOLA POINT) | SEPARABLE ELEMENT | 99-662 | 858 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 8,434,881 |
HI | FRM | POH | HI 1 | WAIKIKI EROSION CONTROL, HI | PROJECT | 89-298 | 301 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 16,584,000 |
IL | EI | LRC | IL 11 & 14 | AURORA, IL | PROJECT | 106-554 | 108d | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 8,000,000 |
IL | FRM | LRC | IL 9, 10 & 14 | DES PLAINES RIVER, IL (NORTH FORK MILL CREEK DAM MODIFICATION) | SEPARABLE ELEMENT | 106-53 | 101b10 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 5,795,400 |
IN | EI | LRE | IN 3 | FORT WAYNE, IN | PROJECT | 106-554 | 108a | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,529,324 |
IN | EI | LRL | IN 7 | INDIANAPOLIS, IN | PROJECT | 106-554 | 108a | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,543,324 |
KY | FRM | LRH | KY 5 | BEAVER CREEK BASIN, KY | PROJECT | 89-298 | 204 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 20,873,500 |
KY & TN | AER | MVM | TN 8; KY 1 | REELFOOT LAKE, TN & KY | PROJECT | 106-53 | 101b11 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 33,072,769 |
LA | FRM | MVK | LA 1 | PEARL RIVER, SLIDELL, SAINT TAMMANY PARISH, LA | PROJECT | 99-662 | 401b | CONSTRUCTION NOT INITIATED | 2002 | 29,311,000 |
LA | FRM | MVN | LA 1, 2 & 6 | AMITE RIVER AND TRIBUTARIES, LA | PROJECT | 102-580 | 101(11) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 38,058,405 |
LA | FRM | MVN | LA 6 | BAYOU COCODRIE AND TRIBUTARIES, LA | PROJECT | 93-251 | 87 | CONSTRUCTION PAUSED | 1987 | 345,472,000 |
LA | NAV | MVN | LA 1, 2, 3 & 6 | GULF INTRACOASTAL WATERWAY, LA-TX SECTION, LA & TX | PROJECT | 87-874 | 101 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 201,422,000 |
LA | EI | MVN | LA 1 & 2 | KENNER, LA | PROJECT | 106-554 | 108 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 5,000,000 |
LA | EI | MVN | LA 1 & 2 | ST. CHARLES, ST. BERNARD, AND PLAQUEMINES PARISHES, LA | PROJECT | 106-554 | 108a | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,543,324 |
LA | EI | MVN | LA 2 & 6 | ST. JOHN THE BAPTIST AND ST. JAMES PARISHES, LA | PROJECT | 106-554 | 108a | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,543,324 |
LA | FRM | MVN | LA 1 | TANGIPAHOA, TCHEFUNCTE, AND TICKFAW RIVERS, LA | PROJECT | 99-662 | 401 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 21,723,000 |
MA | EI | NAE | MA 9 | FALL RIVER AND NEW BEDFORD, MA | PROJECT | 106-554 | 108c | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 35,000,000 |
MA | FRM | NAE | MA 4, 7 & 8 | MUDDY RIVER, BROOKLINE AND BOSTON, MA (AQUATIC ECOSYSTEM RESTORATION FEATURES) | SEPARABLE ELEMENT | 106-541 | 522 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 24,050,000 |
MI | NAV | LRE | MI 1 | ALPENA HARBOR, MI (25 FOOT CHANNEL) | PROJECT | 104-303 | 363d | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 4,063,120 |
MI | NAV | LRE | MI 5 | BAY CITY, MI | PROJECT | 101-640 | 105 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 8,466,275 |
MI | EI | LRE | MI 6 | BENTON HARBOR, ST JOSEPH WASTEWATER TREATMENT PLANT, ST JOSEPH, MI | PROJECT | 106-554 | 108d | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,500,000 |
MI | NAV | LRE | MI 1 | CHARLEVOIX, MI (REVETMENT CONNECTION) | SEPARABLE ELEMENT | 106-53 | 373 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 52,500 |
MI | NAV | LRE | MI 1 | ONTONAGON HARBOR, ONTONAGON COUNTY MI | PROJECT | 104-303 | 363e | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 37,134,623 |
MI | FRM | LRE | MI 5 | SAGINAW RIVER AND TRIBUTARIES, MI (CASS RIVER AT VASSAR) | SEPARABLE ELEMENT | 106-53 | 364(3) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 13,909,394 |
MI | FRM | LRE | MI 4 & 5 | SAGINAW RIVER AND TRIBUTARIES, MI (CURTIS ROAD BRIDGE) | SEPARABLE ELEMENT | 99-662 | 845 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 720,653 |
MI | FRM | LRE | MI 5 | SAGINAW RIVER AND TRIBUTARIES, MI (FLINT RIVER AT FLINT) | SEPARABLE ELEMENT | 104-303 | 329 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 571,781 |
MI | FRM | LRE | MI 4 & 5 | SAGINAW RIVER AND TRIBUTARIES, MI (SHIAWASSEE FLATS) | SEPARABLE ELEMENT | 106-53 | 364(4) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 106,825,583 |
MI, MN & WI | NAV | LRE | MI 1; MN 8; WI 7 | GREAT LAKES CONNECTING CHANNELS & HARBORS, MN, MI & WI | PROJECT | 101-640 | 101a15 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 17,938,174 |
MN | NAV | LRE | MN 8 | DULUTH, MN (ALTERNATIVE TECHNOLOGY PROJECT) | PROJECT | 104-303 | 541a/b | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,000,000 |
MN | EI | LRE | MN 8 | LAKE SUPERIOR CENTER, MN | PROJECT | 104-303 | 542 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 10,000,000 |
MN | EI | MVP | MN 5 | MISSISSIPPI PLACE, MN | PROJECT | 106-53 | 577 | CONSTRUCTION NOT INITIATED | 2006 | 2,968,178 |
MN & WI | NAV | LRE | MN 8; WI 7 | DULUTH-SUPERIOR CHANNEL EXTENSION, MN & WI | PROJECT | 99-662 | 201a | CONSTRUCTION PAUSED | 1995 | 14,064,481 |
MO | EI | NWK | MO 4 & 6 | KANSAS CITY, MO | PROJECT | 106-53 | 502b | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 15,000,000 |
MO & IL | NAV | MVS | MO 1, 2, 3, & 8; IL 12 & 13 | ST LOUIS HARBOR, MO & IL | PROJECT | 99-662 | 601a | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 43,253,100 |
MS | FRM | MVK | MS 2 | YAZOO BASIN, TRIBUTARIES, MS | PROJECT | 89-298 | 204 | CONSTRUCTION PAUSED | 2007 | 233,490,728 |
MS | NAV | MVK | MS 2 | YAZOO RIVER, MS (SHEPARDSTOWN BRIDGE) | SEPARABLE ELEMENT | 99-662 | 822 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 2,011,094 |
MS & LA | AER | MVN | LA 2 | MISSISSIPPI AND LOUISIANA ESTUARINE AREAS, MS & LA | PROJECT | 100-676 | 3(a)8 | CONSTRUCTION NOT INITIATED | 2003 | 70,668,540 |
NC | EI | SAW | NC 8 | LUMBERTON, NC | PROJECT | 106-53 | 502b | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,700,000 |
NC | EI | SAW | NC 8 & 9 | UNION COUNTY, NC | PROJECT | 106-554 | 108a | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,543,324 |
NC & SC | FRM | SAW | NC 9 & 12 | SUGAR CREEK BASIN, NC & SC | PROJECT | 99-662 | 401a | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 54,523,100 |
NH | EI | NAE | NH 2 | NASHUA, NH (COMBINED SEWER OVERFLOW) | PROJECT | 106-53 | 502b | CONSTRUCTION NOT INITIATED | NO OBLIGATION FOR CONSTRUCTION | 19,853,000 |
NH | EI | NAE | NH 1 | ROCHESTER, NH | PROJECT | 104-303 | 504(e) (4) | CONSTRUCTION NOT INITIATED | NO OBLIGATION FOR CONSTRUCTION | 10,897,120 |
NJ | EI | NAN | NJ 8 | ELIZABETH, NJ | PROJECT | 106-53 | 502(f) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 20,000,000 |
NJ | EI | NAN | NJ 8 | NORTH HUDSON, NJ | PROJECT | 106-53 | 502(f) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 20,000,000 |
NJ | EI | NAN | NJ 9 | PATTERSON AND PASSAIC COUNTY, NJ | PROJECT | 106-554 | 108c | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 30,000,000 |
NJ | EI | NAP | NJ 4, 6 & 12 | STATE OF NEW JERSEY AND NEW JERSEY WASTEWATER TREATMENT TRUST, NJ | PROJECT | 102-580 | 219c (10) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,543,324 |
NJ | EI | NAP | NJ 5 | TOWN OF NEWTON, NJ | PROJECT | 106-554 | 108d | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 7,000,000 |
NV | FRM | SPL | NV 4 | LAS VEGAS WASH AND TRIBUTARIES, NV | PROJECT | 102-580 | 101(13) | CONSTRUCTION NOT INITIATED | NO OBLIGATION FOR CONSTRUCTION | 3,360,938 |
NV | FRM | SPL | NV 4 | LAS VEGAS, NV | PROJECT | 109-103 | 115 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 20,000,000 |
NY | EI | LRB | NY26 & 27 | ERIE COUNTY, BUFFALO AMHRST, NY | SEPARABLE ELEMENT | 102-580 | 221 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 7,000,000 |
NY | EI | LRB | NY 26 & 27 | ERIE COUNTY, NY (SLUDGE DISPOSAL) | PROJECT | 102-580 | 219c (12) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,543,324 |
NY | EI | LRB | NY 26 & 27 | ERIE COUNTY, NY (WATER QUALITY TUNNEL) | PROJECT | 102-580 | 219c (11) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,543,324 |
NY | EI | LRB | NY26 & 27 | LEWISTON STORMWATER, NY | SEPARABLE ELEMENT | 102-580 | 222 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 200,000 |
NY | EI | LRB | NY 24 | LIVERPOOL, NY | PROJECT | 106-554 | 108d | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 2,000,000 |
NY | EI | NAN | NY 10 & 11; NJ 8 | INNER HARBOR PROJECT, NEW YORK, NY | PROJECT | 106-53 | 502(f) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 15,000,000 |
NY | FRM | NAN | NY 17, 18, 19 & 20 | LOWER HUDSON RIVER & TRIBUTARIES, NY | PROJECT | 106-53 | 212e | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 30,000,000 |
NY | EI | NAN | NY 6 & 11 | OUTER HARBOR PROJECT, NEW YORK, NY | PROJECT | 106-53 | 502(f) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 15,000,000 |
NY/NJ | NAV | NAN | NJ 6, 9 & 13; NY 7, 8, 9, 12, 13,14 & 15 | NEW YORK HARBOR COLLECTION AND REMOVAL OF DRIFT, NY & NJ | PROJECT | 101-640 | 102 | CONSTRUCTION PAUSED | 2005 | 201,549,768 |
OH | NAV | LRB | OH 9 | OTTAWA RIVER HARBOR, OH | PROJECT | 101-640 | 107a7 | CONSTRUCTION NOT INITIATED | 2006 | 13,218,200 |
OH | FRM | LRH | OH 15 | HOCKING RIVER, LOGAN, OH | PROJECT | 99-662 | 401a | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 16,282,709 |
OH | FRM | LRL | OH 8 | MIAMI RIVER BASIN, PLEASANT RUN, VICINITY FAIRFIELD, OH | PROJECT | 99-662 | 401a | CONSTRUCTION NOT INITIATED | NO OBLIGATION FOR CONSTRUCTION | 18,041,480 |
OK | HYD | SWT | OK 2 | FORT GIBSON LAKE, OK (POWER UNITS 5 & 6) | SEPARABLE ELEMENT | 99-662 | 601a | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 45,485,000 |
OR | EI | NWP | OR 1 | ASTORIA, OR | PROJECT | 106-53 | 502b | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 5,000,000 |
OR | EI | NWP | OR 2 | HOOD RIVER, OR | PROJECT | 106-554 | 108a (36) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,543,324 |
OR | EI | NWP | OR 2 | MEDFORD, OR | PROJECT | 106-554 | 108a (37) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,543,324 |
OR | EI | NWP | OR 1 & 2 | PORTLAND, OR | PROJECT | 106-554 | 108a (38) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,543,324 |
PA | EI | LRP | PA 5 | COUDERSPORT, PA | PROJECT | 106-554 | 108 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,543,324 |
PA | EI | LRP | PA 18 | FINDLAY TOWNSHIP, PA | PROJECT | 106-53 | 502 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 11,000,000 |
PA | EI | LRP | PA 9 | GREENSBORO AND GLASSWORKS, PA | PROJECT | 102-580 | 219c(15) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,543,324 |
PA | EI | LRP | PA 9 | JEFFERSON TOWNSHIP, GREENE COUNTY, PA | PROJECT | 106-53 | 502 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,000,000 |
PA | EI | LRP | PA 18 | NORTH FAYETTE TOWNSHIP, ALLEGHENY COUNTY, PA | PROJECT | 106-53 | 502 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 500,000 |
PA | EI | LRP | PA 18 | ROBINSON TOWNSHIP, PA | PROJECT | 106-53 | 502 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,200,000 |
PA | EI | LRP | PA 14 | SPRINGDALE BOROUGH, PA | PROJECT | 106-53 | 502 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 500,000 |
PA | EI | LRP | PA 3 | TITUSVILLE, PA | PROJECT | 106-554 | 108 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 7,300,000 |
PA | EI | LRP | PA 9, 12, 14 & 18 | WASHINGTON, GREENE, WESTMORELAND, AND FAYETTE COUNTIES, PA | PROJECT | 106-554 | 108 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 8,000,000 |
PA | EI | NAB | PA 10 | BRADFORD AND SULLIVAN COUNTIES, PA | SEPARABLE ELEMENT | 106-53 | 548 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 13,000,000 |
PA | EI | NAB | PA 11 & 15 | DAUPHIN COUNTY, PA | PROJECT | 106-53 | 502b | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 2,000,000 |
PA | EI | NAB | PA 4 | DILLSBURG BOROUGH AUTHORITY, PA | PROJECT | 106-53 | 502b | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 2,000,000 |
PA | EI | NAB | PA 4 | HAMPDEN TOWNSHIP, PA | PROJECT | 106-53 | 502b | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 3,000,000 |
PA | EI | NAB | PA 4 & 11 | MOUNT JOY TOWNSHIP AND CONEWAGO TOWNSHIP, PA | PROJECT | 106-554 | 108d | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 8,300,000 |
PA | EI | NAB | PA 5 | PATTON TOWNSHIP, PA | PROJECT | 106-53 | 502b | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,400,000 |
PA | EI | NAB | PA 4 | UPPER ALLEN TOWNSHIP, PA | PROJECT | 106-53 | 502b | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 3,400,000 |
PA | FRM | NAP | PA 17 | DELAWARE RIVER BASIN-WABASH CREEK, BOROUGH OF TAMAQUA, PA | PROJECT | 93-251 | 2 | CONSTRUCTION NOT INITIATED | 1993 | 13,194,000 |
PA | FRM | NAP | PA 2 & 3 | PHILADELPHIA, PA (FRANKFORD DAM) | PROJECT | 104-303 | 564e | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 900,000 |
PA | FRM | NAP | PA 1, 2, 3 & 13 | PHILADELPHIA, PA (PENNYPACK PARK) | PROJECT | 104-303 | 564d | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 15,000,000 |
PA | FRM | NAP | PA 2 & 3 | PHILADELPHIA, PA (WATER WORKS RESTORATION) | PROJECT | 104-303 | 564a | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,000,000 |
PA | EI | NAP | PA 6 | PHOENIXVILLE BOROUGH, CHESTER COUNTY, PA | PROJECT | 106-554 | 108d | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 2,400,000 |
PA | EI | NAP | PA 8 | TOWAMENCIN TOWNSHIP, PA | PROJECT | 106-53 | 502b | CONSTRUCTION NOT INITIATED | 2005 | 1,462,000 |
PR | FRM | SAJ | PR AT LARGE | GUANAJIBO RIVER, PR | PROJECT | 106-53 | 101 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 33,495,941 |
PR | FRM | SAJ | PR AT LARGE | RIO NIGUA AT SALINAS, PR | PROJECT | 106-53 | 101 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 12,145,000 |
RI | EI | NAE | RI 2 | CRANSTON, RI | PROJECT | 101-640 | 54 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 6,000,000 |
RI | EI | NAE | RI 1 & 2 | DREDGING OF SALT PONDS IN THE STATE OF RHODE ISLAND, RI | PROJECT | 106-53 | 578 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 1,100,000 |
SC | EI | SAC | SC 1 | CHARLESTON, SC | PROJECT | 108-137 | 127 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 10,000,000 |
TN | NAV | MVM | TN 9 | MEMPHIS HARBOR, MEMPHIS, TN | PROJECT | 106-53 | 364 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 110,044,000 |
TN | FRM | MVM | TN 8 | NONCONNAH CREEK, TN & MS (EXTENSION) | SEPARABLE ELEMENT | 106-541 | 334 | CONSTRUCTION NOT INITIATED | 2004 | 36,188,000 |
TX | FRM | SWF | TX 8 & 17 | NAVASOTA RIVER BASIN, TX (MILLICAN LAKE, TX) | SEPARABLE ELEMENT | 90-483 | 203 | CONSTRUCTION NOT INITIATED | 1983 | 778,421,000 |
TX | FRM | SWF | TX 2, 8 & 14 | TRINITY RIVER AND TRIBUTARIES, TX (LIBERTY LOCAL PROTECTION PROJECT) | SEPARABLE ELEMENT | 108-447 | 116 | CONSTRUCTION NOT INITIATED | 1981 | 19,985,000 |
TX | NAV | SWF | TX 2, 8 & 14 | TRINITY RIVER AND TRIBUTARIES, TX (NAVIGATION CHANNEL ABOVE LIBERTY) | SEPARABLE ELEMENT | 108-447 | 116 | CONSTRUCTION NOT INITIATED | 1981 | 5,412,060,000 |
TX | FRM | SWF | TX 2, 8 & 14 | TRINITY RIVER AND TRIBUTARIES, TX (WEST FORK FLOODWAY) | SEPARABLE ELEMENT | 108-447 | 116 | CONSTRUCTION NOT INITIATED | 1981 | 119,408,000 |
TX | FRM | SWG | TX 2, 7, 8, 10, 18 & 29 | BUFFALO BAYOU AND TRIBUTARIES, TX (HALLS BAYOU) | SEPARABLE ELEMENT | 101-640 | 101(21) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 112,536,000 |
TX | FRM | SWG | TX 15 & 34 | LOWER RIO GRANDE BASIN, TEXAS (SOUTH MAIN CHANNEL), TX | SEPARABLE ELEMENT | 99-662 | 401a | CONSTRUCTION NOT INITIATED | 2005 | 207,183,000 |
TX & OK | NAV | SWT | TX 4; OK 2 | RED RIVER WATERWAY (BANK STABILIZATION FEATURES) | SEPARABLE ELEMENT | 90-483 | 101 | CONSTRUCTION NOT INITIATED | 2004 | 685,324,228 |
UT | EI | SPK | UT 1 | CACHE COUNTY, UT | PROJECT | 106-53 | 502b | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 5,000,000 |
UT | FRM | SPK | UT 4 | UPPER JORDAN RIVER, UT | PROJECT | 106-53 | 357 | CONSTRUCTION NOT INITIATED | 2004 | 11,087,268 |
VA | FRM | LRH | VA 9 | LEVISA AND TUG FORKS AND UPPER CUMBERLAND RIVER VA, WV, KY (HAYSI LAKE, VA) | SEPARABLE ELEMENT | 104-303 | 353 | CONSTRUCTION NOT INITIATED | 1989 | 185,915,319 |
VA | NAV | NAO | VA 3 | NORFOLK HARBOR ANCHORAGES, VA | PROJECT | 101-640 | 107a13 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 63,130,000 |
VA | FRM | NAO | VA 2 | WALLOPS ISLAND, VA | PROJECT | 106-53 | 567 | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 8,000,000 |
WA | REC | NWW | WA 5 | SNAKE RIVER INTERPRETIVE CENTER, CLARKSTON, WA | PROJECT | 108-137 | 124 | CONSTRUCTION NOT INITIATED | 2004 | 3,750,044 |
WA | AER | NWS | WA 1 & 2 | STILLAGUMAISH RIVER BASIN, WA | PROJECT | 106-541 | 101b (27) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 26,047,966 |
WV | FRM | LRH | WV 2 | CABIN CREEK LPP, WV | PROJECT | 99-662 | 601a | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 10,409,900 |
WV | FRM | LRH | WV 3 | ISLAND CREEK BASIN, VICINITY OF LOGAN, WV (NON-STRUCTURAL FEATURES) | SEPARABLE ELEMENT | 99-662 | 401a | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 107,707,600 |
WV | NAV | LRH | WV 1 | WEST VIRGINIA PORT DEVELOPMENT, WV | PROJECT | 106-53 | 557(3) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 24,144,000 |
WV | NAV | LRP | WV 1 | WEIRTON PORT, WV | PROJECT | 106-53 | 557(2) | NEVER FUNDED | NO OBLIGATION FOR CONSTRUCTION | 15,274,778 |
# PROJECTS | 147 | TOTAL | 14,348,670,778 | |||||||
NOTES: | ||||||||||
(1) PROJECT/ELEMENT TYPE: PROJECT = WATER RESOURCES DEVELOPMENT PROJECT AUTHORIZED FOR CONSTRUCTION, INCLUDING AUTHORIZED ENVIRONMENTAL INFRASTRUCTURE ASSISTANCE PROGRAM IN ACCORDANCE WITH WRRDA 2014, SECTION 6001(f)(1)(B). | ||||||||||
(2) PROJECT/ELEMENT PHASE AND STATUS: NEVER FUNDED = NEVER FUNDED FOR CONSTRUCTION, INCLUDING PROJECTS IN PRECONSTRUCTION ENGINEERING AND DESIGN; CONSTRUCTION NOT INITIATED = CONSTRUCTION FUNDED BUT PHYSICAL CONSTRUCTION NOT INITIATED; CONSTRUCTION PAUSED = CONSTRUCTION FUNDED BUT PHYSICAL CONSTRUCTION PAUSED. | ||||||||||
(3) PER PUBLIC LAW 106-541, SEC. 507, NO CRITICAL RESTORATION PROJECT MAY BE INITIATED UNDER THIS SUBSECTION AFTER SEPTEMBER 30, 2005. |
[top]
Authority:
This notice is required by § 6001(c) of the Water Resources Reform and Development Act of 2014, Public Law 113-121, 128 STAT 1346-1347.
Dated: September 30, 2015.
Jo-Ellen Darcy,
Assistant Secretary of the Army (Civil Works).
[FR Doc. 2015-25586 Filed 10-6-15; 8:45 am]