73 FR 44 pgs. 11897-11898 - TransColorado Gas Transmission Company, LLC; Notice of Application

Type: NOTICEVolume: 73Number: 44Pages: 11897 - 11898
Docket number: [Docket Nos. CP05-45-001; CP06-401-001]
FR document: [FR Doc. E8-4169 Filed 3-4-08; 8:45 am]
Agency: Energy Department
Sub Agency: Federal Energy Regulatory Commission
Official PDF Version:  PDF Version

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP05-45-001; CP06-401-001]

TransColorado Gas Transmission Company, LLC; Notice of Application

February 27, 2008.

Take notice that on February 12, 2008 TransColorado Gas Transmission Company, LLC (TransColorado) P.O. Box 281304, Lakewood, Colorado 80228-8304, filed an application pursuant to section 7(c) of the NGA and the Commission's regulations to amend its certificates of public convenience and necessity issued in Docket Nos. CP05-45-000 (111 FERC ¶ 62,224) and CP06-401-000 (119 FERC ¶ 61,069). TransColorado seeks authority to relocate two previously authorized compressor stations pending at the Greasewood Compressor Station in Rio Blanco County, Colorado to a new site approximately six miles west called the Love Ranch Compressor Station, also in Rio Blanco County. TransColorado further seeks authority to construct and operate a new interconnect with Rockies Express Pipeline, LLC. TransColorado states that the reconfiguration will permit TransColorado better to meet the current market needs of producers and shippers.

These filings are available for review at the Commission's Washington, DC offices or may be viewed on the Commission's Web site at http://www.ferc.gov/ using the "e-Library" link. Enter the docket number, excluding the last three digits, in the docket number field to access the document. For assistance, please contact FERC Online Support at ferconlinesupport@ferc.gov or Telephone: 202-502-6652; Toll-free: 1-866-208-3676; or for TTY, contact (202) 502-8659.

Any questions regarding these applications should be directed to Skip George, Manager of Certificates, TransColorado Gas Transmission Company, LLC, P.O. Box 281304, Lakewood, Colorado 80228-8304, phone (303) 914-4969.

Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, within 90 days of this Notice the Commission staff will either: Complete its environmental assessment (EA) and place it into the Commission's public record (eLibrary) for this proceeding; or issue a Notice of Schedule for Environmental Review. If a Notice of Schedule for Environmental Review is issued, it will indicate, among other milestones, the anticipated date for the Commission staff's issuance of the final environmental impact statement (FEIS) or EA for this proposal. The filing of the EA in the Commission's public record for this proceeding or the issuance of a Notice of Schedule for Environmental Review will serve to notify federal and state agencies of the timing for the completion of all necessary reviews, and the subsequent need to complete all federal authorizations within 90 days of the date of issuance of the Commission staff's FEIS or EA.

There are two ways to become involved in the Commission's review of this Project. First, any person wishing to obtain legal status by becoming a party to the proceeding for this project should file with the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10) by the comment date, below. A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 14 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding.

However, a person does not have to intervene to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project and/or associated pipeline. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission's rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest.

Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenters will be placed on the Commission's environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission's environmental review process. Environmental commenters will not be required to serve copies of filed documents on all other parties. However, the non-party commenters will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission's final order.

Protests and interventions may be filed electronically via the Internet in lieu of paper; see 18 CFR 285.2001(a)(1)(iii) and the instructions on the Commission's Web site under the "e-filing" link. The Commission strongly encourages electronic filings.

Comment Date: March 19, 2008.

Kimberly D. Bose,

Secretary.

[FR Doc. E8-4169 Filed 3-4-08; 8:45 am]

BILLING CODE 6717-01-P