72 FR 92 pgs. 27172-27173 - Office of Hazardous Materials Safety; Notice of Delays in Processing of Special Permits Applications

Type: NOTICEVolume: 72Number: 92Pages: 27172 - 27173
FR document: [FR Doc. 07-2343 Filed 5-11-07; 8:45am]
Agency: Transportation Department
Sub Agency: Pipeline and Hazardous Materials Safety Administration
Official PDF Version:  PDF Version

DEPARTMENT OF TRANSPORTATION

Pipeline and Hazardous Materials Safety Administration

Office of Hazardous Materials Safety; Notice of Delays in Processing of Special Permits Applications

AGENCY:

Pipeline and Hazardous Materials Safety Administration (PHMSA), DOT.

ACTION:

List of applications delayed more than 180 days.

SUMMARY:

In accordance with the requirements of 49 U.S.C. 5117(c), PHMSA is publishing the following list of special permit applications that have been in process for 180 days or more. The reason(s) for delay and the expected completion date for action on each application is provided in association with each identified application.

FOR FURTHER INFORMATION CONTACT:

Delmer Billings, Office of Hazardous Materials Special Permits and Approvals, Pipeline and Hazardous Materials Safety Administration, U.S. Department of Transportation, East Building, PHH-30, 1200 New Jersey Avenue, Southeast, Washington, DC 20590-0001, (202) 366-4535.

Key to "Reason for Delay"

1. Awaiting additional information from applicant.

2. Extensive public comment under review.

3. Application is technically complex and is of significant impact or precedent-setting and requires extensive analysis.

4. Staff review delayed by other priority issues or volume of special permit applications.

Meaning of Application Number Suffixes

N-New application.

M-Modification request.

PM-Party to application with modification request.

Issued in Washington, DC, on May 7, 2007.

Delmer Billings,

Director, Special Permits Approvals Programs, Office of Hazardous Materials, Special Permits Approvals.

Application No. Applicant Reason for delay Estimated date of completion
10481-M M-1 Engineering Limited, Bradford, West Yorkshire 4 05-31-2007
14167-M Trinityrail, Dallas, TX 1,3,4 06-30-2007

Application No. Applicant Reason for delay Estimated date of completion
14343-N Valero St. Charles Norco, LA 1 05-31-2007
14423-N Accutest Laboratories, Dayton, NJ 4 05-31-2007
14436-N BNSF Railway Company, Topeka, KS 4 06-30-2007
14385-N Kansas City Southern Railway, Company Kansas City, MO 4 06-30-2007
14402-N Lincoln Composites, Lincoln, NE 1 12-31-2007

[FR Doc. 07-2343 Filed 5-11-07; 8:45am]