70 FR 81 pgs. 22011-22012 - Cantera Gas Company and PVR Gas Pipeline, LLC; Notice of Application

Type: NOTICEVolume: 70Number: 81Pages: 22011 - 22012
Docket number: [Docket No. CP05-122-000 and CP05-123-000]
FR document: [FR Doc. E5-2005 Filed 4-27-05; 8:45 am]
Agency: Energy Department
Sub Agency: Federal Energy Regulatory Commission
Official PDF Version:  PDF Version

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP05-122-000 and CP05-123-000]

Cantera Gas Company and PVR Gas Pipeline, LLC; Notice of Application

April 20, 2005.

Take notice that Cantera Gas Company (Cantera) and PVR Gas Pipeline, LLC (PVR), 3 Radnor Corporate Center, Suite 230, 100 Matson Ford Road, Radnor, Pennsylvania, 19087, filed in Docket Nos. CP05-122-000 and CP05-123-000 on April 11, 2005, an application pursuant to sections 7(b) and 7 (c) of the Natural Gas Act (NGA) and the Commission's Regulations, for authorization (i) for Cantera to abandon its section 7 (c) certificate of public convenience and necessity and blanket certificate under Subpart F of Part 157 of the Commission's Regulations, and (ii) to grant PVR a Section 7 (c) certificate of public convenience and necessity and a blanket certificate under Subpart F of Part 157 of the Commission's Regulations. The authorization is to effectuate Cantera's transfer of its sole 11-mile, 10-inch diameter pipeline, its sole jurisdictional facility, to its affiliate PVR, all as more fully set forth in the application which is on file with the Commission and open to public inspection. This filing may be also viewed on the Web at http://www.ferc.gov using the "eLibrary" link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call (202) 502-8659 or TTY, (202) 208-3676.

Any questions regarding this application should be directed to Randy Lentz, Penn Virginia Resource GP, LLC, the General Partner of Penn Virginia Resource Partners, L.P., 8080 North Central Expressway, Suite 900, Dallas, Texas 75206, at (214) 750-9223 or fax (610) 687-6388.

There are two ways to become involved in the Commission's review of this project. First, any person wishing to obtain legal status by becoming a party to the proceedings for this project should, on or before the comment date stated below, file with the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426, a motion to intervene in accordance with the requirements of the Commission's Rules of Practice and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the NGA (18 CFR 157.10). A person obtaining party status will be placed on the service list maintained by the Secretary of the Commission and will receive copies of all documents filed by the applicant and by all other parties. A party must submit 14 copies of filings made with the Commission and must mail a copy to the applicant and to every other party in the proceeding. Only parties to the proceeding can ask for court review of Commission orders in the proceeding.

However, a person does not have to intervene in order to have comments considered. The second way to participate is by filing with the Secretary of the Commission, as soon as possible, an original and two copies of comments in support of or in opposition to this project. The Commission will consider these comments in determining the appropriate action to be taken, but the filing of a comment alone will not serve to make the filer a party to the proceeding. The Commission's rules require that persons filing comments in opposition to the project provide copies of their protests only to the party or parties directly involved in the protest.

Persons who wish to comment only on the environmental review of this project should submit an original and two copies of their comments to the Secretary of the Commission. Environmental commenters will be placed on the Commission's environmental mailing list, will receive copies of the environmental documents, and will be notified of meetings associated with the Commission's environmental review process. Environmental commenters will not be required to serve copies of filed documents on all other parties. However, the non-party commenters will not receive copies of all documents filed by other parties or issued by the Commission (except for the mailing of environmental documents issued by the Commission) and will not have the right to seek court review of the Commission's final order.

Comments, protests and interventions may be filed electronically via the Internet in lieu of paper. See, 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web site under the "e-Filing" link.

Comment Date: May 11, 2005.

Magalie R. Salas,

Secretary.

[FR Doc. E5-2005 Filed 4-27-05; 8:45 am]

BILLING CODE 6717-01-P